Castellated PCB Soldering: Paste Volume, Placement and Joint Inspection

Castellated PCB soldering joins a module's plated edge terminals to a carrier board. Reliable assembly depends on the complete interface: module terminal, carrier land, surface finish, stencil, paste, placement and thermal process. A visible side fillet is useful evidence, but it is not a complete description of every part of the connection.

This page focuses on assembly and quotation preparation. For carrier-footprint geometry and overlap, use castellated pads. Keeping these pages separate helps the engineer move from dimensional design to a controlled assembly trial.

Plated castellated board edge
Plated castellated board edge. RAYPCB site archive image; illustrative context, not a current inspection or ownership record.

Confirm the module and carrier requirements

Use the exact module drawing, recommended land pattern and assembly guidance. Include underside pads or other interfaces that may not be visible from the edge. The carrier construction and nearby thermal mass can also influence how the assembly behaves during soldering.

Identify any restrictions on process exposure, cleaning or rework from the module supplier. Do not assume that every castellated module can use the same profile or be hand-reworked in the same way. The applicable component information and assembly procedure control those decisions.

Castellated PCB Soldering / geometry and scope
Castellated PCB Soldering / geometry and scope. Original explanatory drawing; schematic geometry, not released manufacturing data or inspection evidence.

Review stencil apertures as part of the interface

The aperture controls the nominal paste cavity, while transfer and later reflow determine the deposited and joined result. Aperture dimensions, stencil thickness, paste and printing conditions need review together. Copying the carrier copper land directly into the paste layer is not always the appropriate design.

The tool calculates ideal rectangular aperture volume and the area ratio defined as opening area divided by aperture-wall area. It uses width, length and stencil thickness. The ratio is a geometric descriptor; the calculator does not assign a universal release-efficiency threshold or guarantee a successful print.

Review itemWhat to establish
InterfaceReview module terminals, carrier lands and any hidden underside connections.
PasteKeep ideal cavity volume, transfer assumptions and measured deposit separate.
InspectionUse criteria and methods appropriate to the complete assembled interface.
QuotationInclude sourcing, stencil, trial and verification responsibilities in the scope.

Castellation aperture volume and area ratio

RAYPCB ENGINEERING

Castellation aperture volume and area ratio

Mask, Surface and Assembly Process
Loading Castellation aperture volume and area ratio…
Using this tool & sharing results

Use the stated units, input limits and model assumptions. Results support an engineering discussion; they do not approve a design, process or production order.

After changing inputs, update the result before using it. Where a download or copy action is available, review that brief and attach or paste it into your enquiry. Opening Contact does not transfer these inputs or send a request.

How to use and share tool results

Use the current inputs and keep the assumptions

Start with the feature or process question you actually need to resolve. Fields are blank until you enter values or deliberately load an illustrative example. Example mode remains labeled after editing, so a sample is not silently presented as verified project data. Clear the example before preparing a project-specific record.

Use the units printed beside each input. Keep the drawing revision, measurement basis and source of any allowance in your controlled project records. A field that asks for a limit expects your agreed requirement; the example is not an IPC threshold or a statement of RAYPCB capability. A numerical result should lead to a focused review, not replace it.

Changing any input invalidates the displayed result and disables its download until you calculate again. The text download contains the current inputs, results and assumptions. Nothing is uploaded, stored in analytics or automatically transferred into the Contact form. You may attach the file manually if it helps explain your enquiry; completing the worksheet is optional.

InputWhat to establish before using it
Review referenceUse a nonconfidential reference to connect this worksheet to the correct design or process revision.
Rectangular aperture width · mmUse the actual stencil opening, not the copper land envelope.
Aperture length · mmThe ideal rectangle has no corner-radius correction.
Stencil thickness · mmArea ratio uses opening area divided by aperture-wall area.
Equal aperturesMixed aperture geometries require separate calculations.
Entered transfer efficiency · percentIllustrative assumption only; use measured or justified data for a real comparison.

Optional cost comparison from your own allowances

Use a quotation or a clearly labeled internal assumption for each input. Keep the quantity, construction and inspection scope the same when comparing alternatives. This uncalibrated planning model adds entered values; it contains no current market rates and does not issue a RAYPCB quotation. You can contact the team without completing it.

RAYPCB ENGINEERING

Entered process and inspection cost scenario

Mask, Surface and Assembly Process
Loading Entered process and inspection cost scenario…
Using this tool & sharing results

Budget outputs are planning scenarios. Check the included costs and rate assumptions; a confirmed quotation requires a review of your files and scope.

After changing inputs, update the result before using it. Where a download or copy action is available, review that brief and attach or paste it into your enquiry. Opening Contact does not transfer these inputs or send a request.

How to use and share tool results

Distinguish ideal volume from measured paste

An entered transfer-efficiency percentage can illustrate how a measured or justified assumption changes estimated deposited volume. It is not supplied as a validated default. The model does not account for paste rheology, separation behavior or interactions between neighboring apertures.

If printing is a concern, measure the actual deposit using the appropriate inspection method and retain the aperture identity. A volume estimate cannot predict a final solder fillet or void distribution on its own. Use the result to compare proposals and identify what the assembly trial needs to measure.

Castellated module and carrier interface example
Castellated module and carrier interface example. RAYPCB site archive image; illustrative context, not a current inspection or ownership record.

Control placement and support

The module needs a placement relationship that preserves the intended land overlap and avoids interference. Review datum, orientation and any support or fixture requirement. A module that sits unevenly may present a different joint geometry from the ideal flat model.

The castellated-pad overlap tool can help screen a one-dimensional tolerance question, but it does not replace placement validation. Keep neighboring components and inspection access in view. A densely packed layout may limit how the joint can be observed or reworked later.

Aperture geometry before printing evidence
Aperture geometry before printing evidence. Original explanatory drawing; schematic geometry, not released manufacturing data or inspection evidence.

Define inspection evidence for the actual joint

Inspect the features required by the applicable assembly acceptance criteria and customer agreement. Side appearance, alignment and solder distribution can provide important observations. Hidden underside connections or other concealed features may require additional methods where relevant.

Do not turn one attractive fillet photograph into a claim that every terminal is acceptable. Keep component reference, sample identity and the relevant process state with the inspection record. If a defect appears repeatedly, separate paste deposition, placement, surface condition and thermal-process hypotheses before changing several variables at once.

Plan rework before it becomes urgent

Determine whether rework is permitted and what module or board restrictions apply. Access, thermal exposure, cleaning and post-rework inspection can all affect feasibility. An unsupported assumption that a module can simply be lifted and replaced may create avoidable damage or an unverified repair.

For production, retain the approved assembly route and any accepted exceptions. If the module or carrier revision changes, review the interface again. Similar external dimensions do not prove that the underside lands, terminal finish or thermal requirements are unchanged.

Build a comparable assembly quotation

Provide the module information, carrier files, quantity, sourcing responsibility and expected inspection scope. State whether stencil engineering, a prototype trial or additional verification is required. Include any fixed customer acceptance requirements before comparing totals.

The optional budget worksheet adds your entered allowances for recurring assembly and lot-level work. It contains no market rate and does not issue a quotation. Use the result to organize a discussion with the PCB Assembly team or contact RAYPCB directly with the actual files. A clear interface and evidence scope are more valuable than an unsupported instant price.

Review the module interface as one connected design

The module drawing, carrier footprint and assembly process describe different parts of one interface. Review them together using the exact revisions. Similar pitch or external dimensions do not establish that two modules have the same terminal geometry, underside lands or assembly restrictions.

Identify the controlling dimensional relationship before calculating a margin. Along-edge pitch, normal displacement, rotation and flatness have different effects. A one-dimensional overlap calculation can clarify one question but cannot approve the full interface. Keep the unmodeled relationships visible in the review.

Coordinate copper, permanent-mask openings and stencil apertures without assuming they share a shape. The intended soldering result depends on both geometry and process. Use measured paste and representative assembly evidence where needed rather than interpreting ideal cavity volume as guaranteed joint volume.

Plan inspection access before the enclosure or neighboring components hide the joint. Visible edge features can provide valuable evidence, while concealed connections may need another method. State what each observation demonstrates and keep the product's applicable acceptance criteria in the record.

Finally, include sourcing, stencil engineering, trial and verification responsibilities in the quotation. A prototype build can resolve open interface questions if those questions are defined beforehand. Preserve the resulting approved construction and evidence for recurring orders, and review changes rather than assuming that an unchanged module name means every relevant requirement remains the same.

Castellated PCB Soldering / release checkpoints
Castellated PCB Soldering / release checkpoints. Original explanatory drawing; schematic geometry, not released manufacturing data or inspection evidence.

Standards, source context and limits

Use the official references for their stated scope and the applicable controlled document for contractual requirements. A public scope page, product description or application note is not a complete acceptance specification. Material-supplier guidance applies to the named material and process; it is not evidence that every option is available for this board.

Agree the document revision, construction, inspection method and any exceptions with the responsible engineering and quality teams. The explanatory drawings and worksheet examples on this page are original planning aids, not factory records, qualification results or compliance certificates.